The Design-Build Contract was awarded January 11, 2008. Major construction milestones will include:

Project Milestone
Expected Completion
Bridge Design & Permitting
Summer 2008
Utility Relocations
Summer 2009
Mobilization & Constructing Workbench
Summer 2008
Construction of Ditches & Trestle
Fall 2008
Construction of New Bridge & Roadway
Summer 2009
Removal of Existing Causeway
Fall 2009

 